Kolpinsky district of Saint Petersburg‑St. Petersburg remains an area of increased attention for SUE TEK SPb.
After the bankruptcy of the previous owner, who transferred thermal networks in a state of critical wear to the balance of the fuel and energy complex, the company’s specialists have already replaced almost 77 km of pipelines here.
In 2024, SUE TEK SPb will update another 29 km of heating networks in the Kolpinsky district. Among the most significant objects of this year are heating networks in the village of Pontonny, as well as in blocks 12, 12B, 15 and 15A Kolpino.
In 2025-2028, it is planned to replace at least 94 km of heating networks in the district – design and survey work is already underway on 19 sites.
At the same time, the company is updating heat sources. In the upcoming heating season of 2024-2025, a new boiler room on Bogaichuka Street in Metallostroy will be put into operation. The boiler house modernization works will be completed in 2025.